Wuhan Huoshenshan Hospital took 10 days to build!
Wuhan Huoshenshan Hospital took 10 days to build!
Location of Wuhan Huoshenshan Hospital
Day 1 --- (January 24th )
Hundreds of excavators arrived at the scene
Land leveling started
Day 2 --- (January 25th)
Wuhan Huoshenshan Hospital
Officially started
Day 3 --- (January 26th)
Complete the basic map of 6 nursing units
And the general plan of hydropower
Day 4 --- (January 27th)
Completed the site leveling
The first batch of box container board house hoisting and building
Day 5 --- (January 28th)
Steel structure of double-deck ward
Taking shape
Day 6 --- (January 29th)
More than 300 box-type frame houses
The installation is complete
The electromechanical pipeline operation starts simultaneously
Day 7 --- (January 30th)
HDPE film laying completed
Sewage treatment room equipment hoisting starts simultaneously
Day 8 --- (January 31st)
90% container assembly has been completed
3000 square meters of skeleton installation
Day 9 --- (February 1st)
Fully launched
Medical equipment installation
Day 10 --- (February 2nd)
Wuhan Huoshenshan Hospital